Swampscott Rail Trail
The Swampscott Rail Trail will be a 2-mile linear park throughout the town for every neighborhood, every resident, and every age. The Rail Trail is about new and better ways to connect our neighborhoods, our residents, and our natural environment. The Rail Trail will run along the National Grid utility corridor starting at Stetson Avenue and running east through the middle of the town to the Marblehead town line and connecting to the Marblehead Rail Trail. The utility corridor is the former Marblehead branch of the Boston & Main Railroad, service of which was ended in 1959.
In May 2017, the Swampscott Town Meeting approved (by a vote of 210 to 56) a warrant article to move forward with the Rail Trail and to provide funding for the design and engineering of the trail as well as the costs for the acquisition of the easement rights. This warrant article was unanimously sponsored by the Board of Selectmen and supported by the Finance Committee, Capital Improvement Committee, School Committee, Planning Board, Open Space & Recreation Plan Committee, and Conservation Commission.
In June 2017, a town-wide election was held to bring the question of the Rail Trail project to the entire community. Swampscott voters affirmed Town Meeting's approval by a margin of 12%.
DESIGN & ENGINEERING
The Town of Swampscott has retained the services of STV Inc. to lead the design and engineering phase of the rail trail development.
Schedule
Below is the current schedule for the development of the design and engineering plans for the future Swampscott Rail Trail.
TASK | TIMING | STATUS |
---|---|---|
Notice to Proceed | October 2017 | COMPLETE |
Design Charrettes w/ Trail Neighbors and Public | Nov 7 & 9, 2017 | COMPLETE |
Delineate Wetlands | November 20 & 21, 2017 | COMPLETE |
Aerial and Ground Survey Work | Dec 4-8, 2017 | COMPLETE |
Road Crossing Survey Work (onsite) | Dec 20-27, 2017 | COMPLETE |
Utility Corridor Survey Work (onsite) | Dec 28, 2017-Jan 11, 2018 | COMPLETE |
Complete Survey/Base Plan | Oct 2017 - Jan 2018 | COMPLETE |
Trail Alignment Presentation - with Trail Neighbors | Apr 12, 2018 | COMPLETE |
Site Walk w/ Town Departments, Stantec, and National Grid | May 2018 | COMPLETE |
25% Design Submission | TBD | |
25% Design Public Hearing | TBD | |
75% Design Submission | TBD | |
100% Design Submission | TBD | |
Conservation Commission - Notice of Intent | TBD | |
Right of Way (ROW) Plans | TBD | |
Develop Bid Documents (plans/specifications/estimate) | TBD | |
Issue Bid for Construction | TBD | |
Award Contract | TBD | |
Start Construction | TBD |
Presentations
If you aren't able to attend the public meetings that are part of the design & engineering phase of the rail trail (such as meetings of the Rail Trail Design & Construction Advisory Committee or public forums), you can use the links below to download the presentation files from those meetings.
DATE | MEETING | FILE |
---|---|---|
October 11, 2017 | Rail Trail Design & Construction Advisory Committee Meeting | Download |
April 12, 2018 | Trail Alignment Presentation to Trail Neighbors | Download |