School Building

Site Plan Special Permit from the Planning Board under Swampscott Zoning Bylaw Section 5.4.0.0.
and
Order of Conditions from the Conservation Commission under the Wetlands Protection Act (M.G.L c. 131 §40)
and
Earth Removal Permit from the Earth Removal Advisory Committee under Article XIII Earth Removal Section 3(b) of the Swampscott General Bylaws

 

Applicant: Town of Swampscott
22 Monument Ave.
Swampscott, MA 01907
 
Project Architect: Lavallee-Brensinger Architects
99 Bedford St.
Boston, MA 02111
 
Wetlands Engineer: Nitsch Engineering
2 Center Plaza, Suite 430
Boston, MA 02108

PROJECT UPDATES

11/23/22 - Photos of Stanley School Demolition
07/01/22 - Traffic Circulation Plans During Temporary Relocation of Stanley School Students

SITE PLAN APPLICATION DOCUMENTS

Application and Project Description
Architectural Drawings
Drainage Report
Traffic Impact Report

NOTICE OF INTENT DOCUMENTS

Notice of Intent
Drawings and Plans

Stormwater Report

Peer Review - Linden Engineering
Peer Review Response - Nitsch Engineering
Peer Review Update - Linden Engineering
Special Order of Conditions for New School
Resident Appeal of Order of Conditions

EARTH REMOVAL PERMIT APPLICATION DOCUMENTS

Final Permit
Application
Project Narrative
Permit Drawings and Plans
Appendix A
Expert Blasting Recommendations
Frequently Asked Questions